Renovation
Phase I of the renovation (March 2017 – June 2017)
- 3 viewing jetties, 10 x 5 m, including
lighting - an adventure footbridge to the
islet - a wooden gazebo on the islet -
a gate for lovers on the
islet - 5 reed
parasols - a sandy
beach - bank
reinforcement- palisade
walls - benches made from railway
sleepers - children’s water play area -
lighting along the
banks - exploratory borehole for
water - walkway around the bank made from prefabricated paving slabs -
coloured paint finish on concrete areas for children
Phase II of the renovation (09/17 – 06/18)
- facilities building (toilets, sports equipment storage, refreshment area with seating)
- inline skating track (the route will run from the facilities building, past the lower entrance to the open-air cinema, the skatepark, the Junior Club, Fialova Pond and back to the Nový Pond complex along the old Milínská road)
–
skatepark – Junior Club