Changes to the building prior to completion
Opening hours
Contact
Address
1st floor
Where you can sort this out
Building Control and Town Planning Department, Příbram Municipal Authority
Basic information
A change to a building before its completion may be authorised either before construction begins or whilst construction is in progress. A change to a building prior to its completion may only be authorised in accordance with the planning permission or another instrument replacing the planning permission; if the change to the building prior to its completion requires an amendment to the planning permission, a decision on this amendment may be made in a combined procedure. The planning authority may, at the request of the developer or their legal successor, authorise a change to a building before its completion.
Other necessary documents, information, etc.
Completed application form + other documents listed in Part B of the application form
The form
is available from the building authority, Na Příkopech 105, Příbram I,
or can be downloaded here: Application for a change to a building prior to completion
Legislation governing the procedure
- Act No. 183/2006 Coll., on spatial planning and building regulations, the Building Act.
- Decree No. 501/2006 Coll., on general requirements for land use.
- Decree No. 503/2006 Coll., on more detailed provisions governing spatial planning decisions, spatial planning measures and building regulations.
- Decree No. 268/2009 Coll., on technical requirements for buildings.
Related legislation
- Act No. 500/2004 Coll., the Administrative Procedure Code.
- Act No. 634/2004 Coll., on Administrative Fees.
Further information
On the Building Authority’s website – here
Responsibility for the accuracy of these instructions lies with
Ing. Petr Nováček – Building Authority officer