Pribram.eu Potřebuji vyřídit Životní prostředí, les a rybářství Životní prostředí Voda a studny Wastewater treatment plants for up to 50 PE – notification of CE-marked products
Životní prost. Voda a studny Či. od. vod d.
Wastewater treatment plants up to 50 PE – notification of CE-marked products
- Notification of CE-marked products
Where to deal with this matter:
Příbram Town Hall, Tyršova 108, 261 19 Příbram, Environment Department
Basic information:
To construct waterworks intended for the treatment of waste water with a capacity of up to 50 population equivalents, a significant part of which consists of products bearing the CE marking in accordance with the Act on Technical Requirements for Products, it is sufficient to submit a notification to the water authority.
Procedure:
The water authority may, by decision, prohibit the construction of the notified structure. The time limit for prohibiting the construction of the notified structure is 30 days.
Who is authorised to submit an application, notification, etc.:
The developer or their representative (on the basis of a power of attorney).
Form: where to obtain it:
A hard copy of the application form can be obtained from the Department of the Environment and on the town’s website.
Download here:
Legislation governing the procedure:
- Act No. 500/2004 Coll., the Administrative Procedure Code
- Act No. 183/2006 Coll., on Spatial Planning and the Building Code (the Building Act)
Act No. 254/2001 Coll., on Water - Act No. 500/2004 Coll., the Administrative Procedure Code
- Decree No. 183/2018 Coll., on the requirements for decisions and other measures of the water authority and on documents to be submitted to the water authority
Requirements for the application:
See the relevant form.
Administrative (or other) fee:
approval of the notification – 400 Kč
Responsible for the accuracy of these instructions: Ing. Miloš Dubovský
Updated: 1. 11. 2018 v 10:23:09