Application for final building approval (organisation)

Where to deal with this matter:
Building Control and Town Planning Department, Příbram Municipal Authority,
at the following address: Na Příkopech 105, Příbram I, 261 01 Příbram 1
, 1st floor (on the right and left at the front of the building).

Basic information:
An application for final building approval must be submitted for buildings for which planning permission was granted by 31 December 2006.

Other required documents, information, etc.:
Completed application form + other documents specified in the application form

The form is available: at the Building Authority, Na Příkopech 105, Příbram I, 1st floor
, or can be downloaded here: final inspection (organisation) – form

Legislation governing the procedure:
Act No. 50/1976 Coll., on Spatial Planning and Building Regulations, the Building Act.

Related legislation:
Act No. 500/2004 Coll., the Code of Administrative Procedure.
Act No. 634/2004 Coll., on Administrative Fees.

Where to find further information:
On the building authority’s website – here – or by calling 318 402 461 – 471

Responsible for the accuracy of these guidelines:
Ing. Petr Nováček – Building Authority Officer

 