Project timeline
| Decision to revitalise the square following an architectural competition | 2019 |
| Public involvement in the terms of reference for the architectural competition (organised by Agora CE) | 2020 |
| Preparation of the terms of reference for the architectural competition (organised by CCEA MOBA) | 2021 |
| Architectural competition | 2022 |
| Review of the competition results and revision of the study | 2023 |
| Finalisation of the building design | May 2024 |
| Documentation for planning permission | 04/2025 |
| Granting of planning permission | 10/2026 |
| Preparatory documentation for geotechnical investigation and remediation | 12/2025 |
| Construction documentation | 04/2027 |
| Implementation | 2027–2029 |
Updated: 31. 5. 2026 v 22:03:10