Pribram.eu O městě Ekonomika města Dotace a granty Dotace získané městem Ministerstvo průmyslu a obchodu ČR Modernisation of the public lighting system in the town of Příbram – Phase V
Dot. získ. mě. Minis. pr. a. Mode. VO ve m.
Modernisation of public lighting in the town of Příbram – Phase V
| Project title | Modernisation of public lighting in the town of Příbram – Phase V |
| Project registration number | 2182000896 |
| Programme | NATIONAL RECOVERY PLAN, component 2.2.2 |
| Brief description of the project | This project is co-financed by the European Union under the National Recovery Plan; the grant provider is the Ministry of Industry and Trade of the Czech Republic. The title of the application is ‘Modernisation of public lighting in the town of Příbram – Phase V”, application registration number 2182000896 from Call No. NPO 1/2022: Reconstruction of public lighting. Due to the unsatisfactory current condition of the public lighting, a complete reconstruction of the public lighting system was carried out, consisting of the replacement of luminaires. A total of 897 luminaires were replaced, 5 luminaires were added, and 6 luminaires were removed without replacement. The level of illumination or brightness of the road surface complies with the values required by the ČSN EN 13201 standard, with a deviation of no more than 30 per cent. No part of the luminous flux emitted by a luminaire is directed above the horizontal plane passing through the centre of the luminaire. Switchboards: The area is supplied by a total of 14 switchboards. The 14 switchboards in question were replaced and fitted with a control system. Street lighting structural elements: 113 street lighting columns were replaced, 8 column extensions were fitted, and 20 brackets were removed. The complete modernisation has therefore delivered energy savings of 78.49 per cent compared with the pre-renovation situation, whilst also reducing light pollution. |
| Total expenditure on the project | CZK 19,222,369.76 incl. VAT |
| Total grant awarded | CZK 10,000,000.00 |
| Co-financing from the city’s resources (including ineligible expenditure) | CZK 9,222,369.76 |
| Implementation period | October 2024 – May 2025 |
Updated: 28. 1. 2025 v 14:39:06